Symptom
The sustainer payment is not selected when a payment has been processed and the process month and day is greater than the due month and day unless a range of due dates is used
Cause
Cause: The issue has been confirmed as a product defect and has been reported to our Research and Development team
Resolution
Workaround: Enter in a range of due dates

Please refer to KB article 4771-Scheduled fixes  to see if this is scheduled for a fix.
 
Article Type
Product Issue
Product Line
Millennium
Product Module/Feature
Sage Payment Solutions
Product Version
2017.1.3